- Central Railway's Pune-Miraj Doubling Project Finally Complete
Central Railway's Pune-Miraj Doubling Project Finally Complete
Railways to Run at Speed on the Pune-Miraj Route; 280 km of Doubling Work Finished, Speed Set to Increase
The crucial 280-kilometer stretch of the Central Railway's ambitious Pune-Miraj doubling project has finally been completed. After the final segment between Koregaon-Rahimatpur-Targaon was finished, the Commissioner of Railway Safety (CMR) inspected the route and granted permission for trains to run at a speed of 100 kilometers per hour.
PUNE, 20 NOV. The crucial 280-kilometer stretch of the Central Railway's ambitious Pune-Miraj doubling project has finally been completed. After the final segment between Koregaon-Rahimatpur-Targaon was finished, the Commissioner of Railway Safety (CMR) inspected the route and granted permission for trains to run at a speed of 100 kilometers per hour.
The Central Railway started the doubling and electrification work on the 280 km Pune-Miraj route in 2016, with a target to complete it by May 2023. While the electrification of the old line was completed, the doubling work faced delays due to objections from farmers regarding land acquisition in Satara and Pune districts, along with other challenges, and work stoppage during the COVID-19 pandemic.
Relief for Railway Passengers and Increased Capacity
The doubling work on the final 21-kilometer stretch between Koregaon-Rahimatpur-Targaon was completed rapidly in recent months. Following the completion, the CMR inspected the route on November 6 and conducted a trial run, during which the train ran at a speed of 130 kmph. With the entire route now doubled, train travel between Pune and Miraj will be faster.
For years, there were complaints regarding overcrowding, frequent delays, and limited capacity on the Pune-Miraj route. The doubling will increase the number of trains and improve punctuality. It is also expected to significantly boost the freight transport capacity. In the future, the route will be equipped for high-speed/semi-high-speed trains. The completion of the project by Central Railway is expected to greatly benefit Konkan, Western Maharashtra, the Karnataka border region, and industrial areas.
Expected Increase in Train Services
Currently, about nine trains run daily on the Pune-Miraj route, including six express and three passenger trains. Eleven express trains also run once a week. Prominent daily trains on this route include the Mahalaxmi, Maharashtra Express, Koyna, and Vande Bharat. The completion of the doubling project is expected to lead to an increase in the number of trains on this route.